Feng shui · Building

Settle feng shui before the drawings: what costs most to change

This article takes no view on which feng shui rules are right — that is for the household and its consultant. It is about timing: which requirements must exist before drawing, which can still change, and which mean demolition if they arrive late.

Written from site experience. Most friction between household, consultant and builder is not disagreement about principles. It is requirements arriving late.

When a change costs what

ItemFix beforeChanging later means
House and main door directionApplying for the permitReapplying, redrawing from scratch
Stair position and number of treadsStructural designDemolishing structure — the costliest
Bathroom and altar room positionsStructural and services designCutting slabs, rerouting waste
Stove direction and hob positionFirst fix servicesChasing walls, rerouting extract
Altar positionElectrical first fixSurface wiring or chasing painted walls
Door swing directionsBlockworkDemolishing and rebuilding openings
Colours by elementOrdering finishesChangeable — only material cost
Ground-breaking and move-in datesSetting the programmeThe whole programme shifts

The first four must be settled before drawing. The rest remain more flexible.

Stairs: the most expensive late change

Counting treads against the cycle Birth – Age – Illness – Death is the most common feng shui requirement in Vietnamese houses, with households wanting the final tread to land on "Birth".

Why changing it late costs so much: the number of treads is tied to the floor-to-floor height. Changing the count changes the riser height, and riser height has a usable range of roughly 15 – 18 cm. Outside that, the floor-to-floor height must change — and that is already in the structural drawings, in the reinforcement, and in the permit.

So a requirement about tread count must be raised at the first meeting, before the architect fixes storey heights.

Stove direction and hob position

Settle before first-fix services. Once pipework is buried and walls plastered, moving the hob means chasing walls.

Two things to check at the same time, and this is where a builder should speak up early:

  • Can extract ducting reach outside from that position? The longer the duct and the more bends, the worse it performs. A favourable direction sometimes lands on an internal wall with no route out.
  • Does the position clash with a window, column or service riser?

How the direction is measured: kitchen orientation in feng shui. The rules and their reasons: kitchen feng shui.

The altar: small, and often forgotten

Altar position tends to come up only near completion, by which point the electrics are done. But an altar needs a socket for lighting, a position clear of a bathroom above or behind, a wall strong enough if it is wall-hung, and headroom free of a beam.

Settled early it is one socket on a drawing. Settled late it is surface wiring, or chasing a painted wall.

Borrowed age, and what it means for the contract

Where the householder's year is deemed unfavourable, custom allows another person's age to be "borrowed" for the ceremonies. That is a family matter, but it touches the contract and the programme, so the builder should know in advance:

  1. Who signs. The person whose age is borrowed stands in for the ceremonies only. They should not be named on the building contract and should have no part in payments. Agreeing this avoids later legal confusion.
  2. Who attends the ground-breaking, and on what date. The builder needs the date to schedule plant and labour.
  3. When the move-in ceremony falls relative to handover. An auspicious date can land a month after completion, or before the house is finished — both need planning for.
The commonest cause of programme slip: ground-breaking and move-in dates chosen after the contract is signed and the programme set. An auspicious date can be three or four weeks from the assumed one, by which time the builder has committed labour elsewhere.

The remedy is simple: have the dates chosen before signing, or tell the builder they are not yet fixed so the programme can be written as "X days after ground-breaking" rather than against calendar dates.

Choosing the year to build

Several traditional systems are used to judge whether a given year suits a householder's age. We do not calculate these — that belongs to a consultant or a published table. A few practical observations:

  • The systems do not always agree. A year can be favourable under one and unfavourable under another.
  • That is partly why many families borrow an age rather than wait.
  • If you do decide to wait, count the cost of waiting: material prices generally rise year on year, and rent paid meanwhile is a real cost.

That last point is not an argument against the tradition. It is so the decision is made with both sides visible.

What to bring to the first meeting

  1. House direction and main door direction
  2. Stove direction — written as "stove backs onto …" or "cook faces …"
  3. Any requirement on the number of stair treads
  4. Altar position or direction
  5. Positions to be avoided: bathrooms, stairs, doors
  6. Colours by element, if required
  7. Ground-breaking and move-in dates, or the expected window

In writing wherever possible, even a handwritten note or a message. A requirement relayed by word of mouth through three people is a requirement that will be misunderstood.

How Tropicity works

We do not offer feng shui readings — no ages, no dates, no directions. That belongs to the consultant the family trusts.

Our part is three things: take the requirements in writing and put them correctly on the drawings; report conflicts immediately between a requirement and the structure, services or how the house will work, so the household and consultant decide before building; and write the ceremony dates into the programme from the contract onwards where they are known.

See 10 questions before signing a design-build contract or what turnkey construction includes.

Send your plan and feng shui requirements

Free preliminary estimate

Get our company profile and a budget range within 48 hours

Tell us where your project is and what you plan to build. A Tropicity engineer replies within one working day and arranges a site visit in Ho Chi Minh City and the southern provinces.

  • One contract, one estimate, one point of contact
  • A structural engineer visits your site
  • English-speaking contact; no marketing emails

Why the site address? Planning rules, building density and truck access change the price. Without the address an estimate is only a generic figure.

Please enter your name.
Please enter a valid email.
Please select a project type.
Please enter the project location.

Urgent: call +84 937 989 858

Zalo