What turnkey construction includes — and what it leaves out
"Turnkey" is the most misleading word in Vietnamese construction. Two companies using it may be selling quite different things. This article sets out what it usually covers and, more usefully, what it usually does not.
What turnkey means here
The owner appoints a single company for the whole construction package — the contractor supplies both materials and labour, and the owner pays an agreed rate, normally per square metre of constructed floor area.
The two common alternatives:
- Labour-only: the owner buys all materials, the contractor supplies the workforce. Cheapest on paper, but it requires the owner's time and knowledge of materials.
- Turnkey structure plus finishing labour: the contractor supplies structural materials and finishing labour; the owner buys the finishing materials — tiles, sanitaryware, paint. Common where owners want to choose those themselves.
What a turnkey package usually covers
- Foundations — excavation, piling where the ground is weak, pile caps, ground beams.
- Structure — columns, beams, slabs, stairs, blockwork, render, waterproofing, services chased into walls.
- Finishes — tiling, paint, plasterboard ceilings, electrical fittings and sanitaryware, balustrades, doors and windows.
- Materials for the above, to a schedule agreed in the contract.
What it usually excludes
- Loose and fitted furniture. Kitchens, wardrobes, beds, curtains, decorative lighting. The industry default is excluded unless the contract says otherwise.
- Building permit costs and legal documentation.
- Architectural and structural design, where the contractor is not the designer.
- Piling — frequently separated, because the number of piles is only known after the ground investigation. Ask whether the price includes a stated length of piling and how any excess is charged.
- Demolition of an existing building and removal of rubble.
- Special systems — lifts, solar, whole-house water treatment, home automation, central air conditioning.
- Garden, pool, gates, boundary walls.
- Utility connections from the public networks.
- Ground-related variations, where the investigation shows weaker soil than assumed.
The questions owners ask most
Does turnkey include the foundations?
Yes, foundations are normally included. But piling is often separated, and it is the largest variation owners meet. Require the contract to state how much piling is included and how any excess is priced.
Does turnkey include interiors and the kitchen?
By default, no. If you want them, they must appear as a separate package with an itemised schedule. One detail is easily missed: the services left ready for the kitchen — socket positions, water supply for the sink, extract ducting. Those belong to the construction works and must be fixed before rendering. If the interiors have not been designed by then, walls get cut open later.
How is the rate calculated?
Usually per square metre of constructed floor area — but how the area is counted is where quotations diverge. For the same house, two contractors can produce different areas because they apply different percentages to foundations, roof, balconies, light wells and basements.
So when comparing, compare the totals, not the rate per square metre. A low rate with a generous area calculation can cost more than a high rate counted strictly.
Eight lines a turnkey contract should contain
- A material schedule naming manufacturer and reference for cement, steel, tiles, paint, sanitaryware, cable and pipework.
- The area calculation method, with the percentage applied to foundations, roof, balconies, yards and basements.
- A list of exclusions — the longer the better for the owner.
- A stage programme with liquidated damages for delay.
- Payments tied to inspection milestones, not to calendar dates.
- A variations procedure: who approves, in what written form, priced against what.
- Warranty periods, with waterproofing stated separately.
- Retention held until the warranty period ends.
See also 10 questions to ask before signing a design-build contract.
How Tropicity works
Tropicity is a design-build main contractor: architecture and structural design, construction, interiors made in our own joinery workshop, and aluminium and glass made in our own window workshop. Because the interiors and the windows come from the same company, the services left ready and the structural openings are fixed on one set of drawings — no reopening walls after rendering.
Our estimates separate construction, interiors and windows into three packages, with an explicit list of exclusions.
Two things we state plainly in every quotation, because they are the two most common sources of dispute:
- Piling is priced outside the turnkey rate, by the quantity actually driven. We do not fold it into the rate per square metre, because doing so either overcharges a building on good ground or runs short on weak ground. The quantity is only known after the ground investigation.
- An area calculation showing the coefficient for each element. You receive a sheet stating what percentage is applied to foundations, roof, balconies, yards and basement, and the converted area each produces — so you can compare against another contractor on the same basis rather than comparing two totals.
See turnkey villas or completed projects.